Seplat Energy has said that the Assa North Ohaji South (ANOH) project will be completed in the third quarter of 2024.
The company stated this in its unaudited financial repfor Q3/2023.
The company stated further that there have been further delays during the construction of the project, particularly on the two critical infrastructure projects managed by third parties: OB3 pipeline and Spur line.
The report stated: “ANOH first gas now expected in 3Q-2024. Further delays during construction of the project, particularly the two critical infrastructure projects managed by third parties: OB3 pipeline and Spur line.”
In the report, Seplat Energy Chief Executive Officer, Roger Brown, said: “Ongoing third-party delays to ANOH’s export infrastructure remain a source of frustration, but we are confident that the quality of the project will support dividend growth for Seplat in the coming years as we diversify the business and deliver on our strategy to provide more affordable energy for Nigeria.”
According to the company’s latest report, in the second quarter of 2023, several important steps were planned for the ANOH gas project.
- SANWO-OLU SIGNS LAGOS ELECTRICITY BILL
- NNPC Committed to Advancing Local Content in Nigeria’s Energy Sector
- TCN Restores Bulk Power Supply via Ahoada-Yenagoa 132kV Line
- NAE, STAC Marine celebrate one year of partnership, sign Pact for Safety
- Hybrid Group graduates 15 HSE trainees in Lagos
These included finishing the AGPC plant’s mechanical work, drilling and connecting upstream wells, crossing a river with the OB3 pipeline, and linking the OB3 pipeline to the ANOH gas plant using a spur line.
However, the project has faced delays due to various factors, including security issues, adverse weather conditions, and performance issues with contractors. Consequently, progress has been slower than initially expected.
Despite these challenges, the AGPC plant is nearing completion, with 95% progress, and the company anticipates achieving mechanical completion by the end of 2023.
Notably, the AGPC project has maintained an impressive safety record, with 10 million man-hours of work completed without any lost-time incidents (LTI).
In the report, Seplat Energy also stated that in the first half of 2023, drilling of the third well was complete, and work on the fourth well is well underway, and expected to finish soon.